Wednesday, 26 October 2011

Frames going up

Frames started going up on Monday with first floor nearly complete. By Tuesday the joist and upper flooring was in place. Despite the showering weather this week, we had more second storey framing happening on Wednesday. Looks like windows still need to go in place on the upper storey and roofing structure. Hopefully the skeleton of the house will be done by Friday. And fingers crossed for bricking to commence the following week.

Saturday, 22 October 2011

Our windows/slide doors

We have chosen APO grey in satin finish. I would imagine one of these sliding doors will go in our rumpus/kitchen leading to the alfresco. And the other for the master bedroom balcony.

Wednesday, 19 October 2011

Monday, 17 October 2011

Frames delivered

Just drove past our land this evening and seems like our frames have been delivered. Can see some wall frames and trusses, joists and some other stuff but no windows yet. Hopefully something with happen this week.

Slab constructed

our slab has been sitting for about 2 weeks now, the only P-Class slab on the street (I think P stands for pricey), every other house got away with a M-Class. This has something to do with the facade and zone of influence.

Building with Firstyle - Newbury 32 @ Hoxton Park

Phong and Alica are building the Newbury 32 (Millennium facade) from Firstyle Homes. It should look something like that but our one is a mirror image with different colour scheme and semi-bagged.